Who selects the appropriate processes for a project?

A.
Project stakeholders
Answers
A.
Project stakeholders
B.
Project sponsor and project stakeholder
Answers
B.
Project sponsor and project stakeholder
C.
Project manager and project team
Answers
C.
Project manager and project team
D.
Project manager and project sponsor
Answers
D.
Project manager and project sponsor
Suggested answer: C