The Verify Scope process is primarily concerned with:

A.
formalizing acceptance of the completed project deliverables.
Answers
A.
formalizing acceptance of the completed project deliverables.
B.
accuracy of the work deliverables.
Answers
B.
accuracy of the work deliverables.
C.
formalizing approval of the scope statement.
Answers
C.
formalizing approval of the scope statement.
D.
accuracy of the work breakdown structure (WBS).
Answers
D.
accuracy of the work breakdown structure (WBS).
Suggested answer: A