Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.
Work breakdown structure
Answers
A.
Work breakdown structure
B.
Organizational breakdown structure
Answers
B.
Organizational breakdown structure
C.
Resource breakdown structure
Answers
C.
Resource breakdown structure
D.
Bill of materials
Answers
D.
Bill of materials
Suggested answer: A