When is a project finished?

A.
After verbal acceptance of the customer or sponsor
Answers
A.
After verbal acceptance of the customer or sponsor
B.
After lessons learned have been documented in contract closure
Answers
B.
After lessons learned have been documented in contract closure
C.
When the project objectives have been met
Answers
C.
When the project objectives have been met
D.
After resources have been released
Answers
D.
After resources have been released
Suggested answer: C