Which of the following involves making information available to project stakeholders in a timely manner?

A.
Plan Communications
Answers
A.
Plan Communications
B.
Performance reporting
Answers
B.
Performance reporting
C.
Project status reports
Answers
C.
Project status reports
D.
Distribute Information
Answers
D.
Distribute Information
Suggested answer: D