What is the name of a graphic display of project team members and their reporting relationships?

A.
Role dependencies chart
Answers
A.
Role dependencies chart
B.
Reporting flow diagram
Answers
B.
Reporting flow diagram
C.
Project organization chart
Answers
C.
Project organization chart
D.
Project team structure diagram
Answers
D.
Project team structure diagram
Suggested answer: C