Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.
Critical path method
Answers
A.
Critical path method
B.
Variance analysis
Answers
B.
Variance analysis
C.
Schedule compression
Answers
C.
Schedule compression
D.
Schedule comparison bar charts
Answers
D.
Schedule comparison bar charts
Suggested answer: A