A procurement management plan is a subsidiary of which other type of plan?

A.
Resource plan
Answers
A.
Resource plan
B.
Project management plan
Answers
B.
Project management plan
C.
Cost control plan
Answers
C.
Cost control plan
D.
Expected monetary value plan
Answers
D.
Expected monetary value plan
Suggested answer: B