An output of the Create WBS process is:

A.
Scope baseline.
Answers
A.
Scope baseline.
B.
Project scope statement.
Answers
B.
Project scope statement.
C.
Organizational process assets.
Answers
C.
Organizational process assets.
D.
Requirements traceability matrix.
Answers
D.
Requirements traceability matrix.
Suggested answer: A