Change requests are an output from which Project Integration Management process?

A.
Direct and Manage Project Execution
Answers
A.
Direct and Manage Project Execution
B.
Develop Project Management Plan
Answers
B.
Develop Project Management Plan
C.
Close Project
Answers
C.
Close Project
D.
Develop Project Charter
Answers
D.
Develop Project Charter
Suggested answer: A