Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

A.
Control chart
Answers
A.
Control chart
B.
Earned value
Answers
B.
Earned value
C.
Variance
Answers
C.
Variance
D.
Trend
Answers
D.
Trend
Suggested answer: D