Which is one of the major outputs of Sequence Activities?

A.
Responsibility assignment matrix (RAM)
Answers
A.
Responsibility assignment matrix (RAM)
B.
Work breakdown structure (WBS) update
Answers
B.
Work breakdown structure (WBS) update
C.
Project schedule network diagram
Answers
C.
Project schedule network diagram
D.
Mandatory dependencies list
Answers
D.
Mandatory dependencies list
Suggested answer: C