List of questions
Related questions
Question 436 - CAPM discussion
Which is one of the major outputs of Sequence Activities?
A.
Responsibility assignment matrix (RAM)
B.
Work breakdown structure (WBS) update
C.
Project schedule network diagram
D.
Mandatory dependencies list
Your answer:
0 comments
Sorted by
Leave a comment first