Which of the following documents allows the project manager to assess risks that may require near term action?

A.
Probability and impact matrix
Answers
A.
Probability and impact matrix
B.
Contingency analysis report
Answers
B.
Contingency analysis report
C.
Risk urgency assessment
Answers
C.
Risk urgency assessment
D.
Rolling wave plan
Answers
D.
Rolling wave plan
Suggested answer: C