Which activity involves ensuring that the composition of a projects configuration items is correct?

A.
Configuration Identification
Answers
A.
Configuration Identification
B.
Configuration Status Accounting
Answers
B.
Configuration Status Accounting
C.
Configuration Verification and Audit
Answers
C.
Configuration Verification and Audit
D.
Configuration Quality Assurance
Answers
D.
Configuration Quality Assurance
Suggested answer: C