In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.
enterprise environmental factors.
Answers
A.
enterprise environmental factors.
B.
organizational process assets.
Answers
B.
organizational process assets.
C.
project management plan,
Answers
C.
project management plan,
D.
project funding requirements.
Answers
D.
project funding requirements.
Suggested answer: A