Question 498 - CAPM discussion

Report
Export

An input to the Perform Quantitative Risk Analysis process is the:

A.
quality management plan.
Answers
A.
quality management plan.
B.
project management plan.
Answers
B.
project management plan.
C.
communications management plan.
Answers
C.
communications management plan.
D.
schedule management plan.
Answers
D.
schedule management plan.
Suggested answer: D