When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
A.
divided among each of the phases or subprojects.
B.
repeated for each of the phases or subprojects.
C.
linked to specific phases or subprojects.
D.
integrated for specific phases or subprojects.