A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

A.
US$S000
Answers
A.
US$S000
B.
US$9500
Answers
B.
US$9500
C.
US$10,000
Answers
C.
US$10,000
D.
US$12,500
Answers
D.
US$12,500
Suggested answer: D