Question 502 - CAPM discussion

Report
Export

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?

A.
Resource leveling and fast tracking
Answers
A.
Resource leveling and fast tracking
B.
Fast tracking and crashing
Answers
B.
Fast tracking and crashing
C.
Crashing and applying leads and lags
Answers
C.
Crashing and applying leads and lags
D.
Scheduling tools and applying leads and lags
Answers
D.
Scheduling tools and applying leads and lags
Suggested answer: A