Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

A.
Limited
Answers
A.
Limited
B.
Low to moderate
Answers
B.
Low to moderate
C.
Moderate to high
Answers
C.
Moderate to high
D.
High to almost total
Answers
D.
High to almost total
Suggested answer: C