Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.
Product scope description
Answers
A.
Product scope description
B.
Procurement statement of work
Answers
B.
Procurement statement of work
C.
Project schedule
Answers
C.
Project schedule
D.
Work breakdown structure (WBS)
Answers
D.
Work breakdown structure (WBS)
Suggested answer: B