As the project progresses, which of the following is routinely collected from the project activities?

A.
Communication management activities
Answers
A.
Communication management activities
B.
Change requests
Answers
B.
Change requests
C.
Configuration verification and audit
Answers
C.
Configuration verification and audit
D.
Work performance information
Answers
D.
Work performance information
Suggested answer: D