Question 522 - CAPM discussion

Report
Export

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

A.
Transfer
Answers
A.
Transfer
B.
Share
Answers
B.
Share
C.
Avoid
Answers
C.
Avoid
D.
Accept
Answers
D.
Accept
Suggested answer: A