To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

A.
scope creep.
Answers
A.
scope creep.
B.
a change request.
Answers
B.
a change request.
C.
work performance information.
Answers
C.
work performance information.
D.
deliverables.
Answers
D.
deliverables.
Suggested answer: A