The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

A.
Executing.
Answers
A.
Executing.
B.
Initiating,
Answers
B.
Initiating,
C.
Monitoring and Controlling.
Answers
C.
Monitoring and Controlling.
D.
Planning.
Answers
D.
Planning.
Suggested answer: C