In which Project Management Process Group is the project charter developed?

A.
Monitoring and Controlling
Answers
A.
Monitoring and Controlling
B.
Executing
Answers
B.
Executing
C.
Initiating
Answers
C.
Initiating
D.
Planning
Answers
D.
Planning
Suggested answer: C