Which is the correct formula for calculating expected activity cost for three-point estimating?
A.
Ce = (C0 + 6Cm + Cp)/4
B.
Ce = (6C0 + Cm + Cp)/4
C.
Ce = (C0 + 4Cm + Cp)/6D. Ce = (C0 + CД, + 4Cp) / 6