Which of the following is an example of schedule compression?

A.
Activity sequencing
Answers
A.
Activity sequencing
B.
Resource leveling
Answers
B.
Resource leveling
C.
Lead and lag adjusting
Answers
C.
Lead and lag adjusting
D.
Crashing
Answers
D.
Crashing
Suggested answer: D