During which process would stakeholders provide formal acceptance of the completed project scope?

A.
Perform Quality Control
Answers
A.
Perform Quality Control
B.
Verify Scope
Answers
B.
Verify Scope
C.
Control Scope
Answers
C.
Control Scope
D.
Develop Schedule
Answers
D.
Develop Schedule
Suggested answer: B