Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

A.
-8000
Answers
A.
-8000
B.
-2000
Answers
B.
-2000
C.
2000
Answers
C.
2000
D.
8000
Answers
D.
8000
Suggested answer: B