Managing procurement relationships and monitoring contract performance are part of which process?

A.
Conduct Procurements
Answers
A.
Conduct Procurements
B.
Plan Procurements
Answers
B.
Plan Procurements
C.
Administer Procurements
Answers
C.
Administer Procurements
D.
Close Procurements
Answers
D.
Close Procurements
Suggested answer: C