Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.
Risk register
Answers
A.
Risk register
B.
Risk data quality assessment
Answers
B.
Risk data quality assessment
C.
Risk categorization
Answers
C.
Risk categorization
D.
Risk urgency
Answers
D.
Risk urgency
Suggested answer: A