Which is an input to the Verify Scope process?

A.
Performance report
Answers
A.
Performance report
B.
Work breakdown structure (WBS)
Answers
B.
Work breakdown structure (WBS)
C.
Requested changes
Answers
C.
Requested changes
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: D