Question 601 - CAPM discussion

Report
Export

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.
The risk of achieving the shortened project time is increased.
Answers
A.
The risk of achieving the shortened project time is increased.
B.
The critical path will have positive total float.
Answers
B.
The critical path will have positive total float.
C.
Contingency reserves are released for redeployment by the project manager.
Answers
C.
Contingency reserves are released for redeployment by the project manager.
D.
Duration buffers are added to maintain a focus on planned activity durations.
Answers
D.
Duration buffers are added to maintain a focus on planned activity durations.
Suggested answer: A