What are the identified risks for doing excessive decomposition in a WBS?

A.
Insufficient project funding and disqualification of sellers
Answers
A.
Insufficient project funding and disqualification of sellers
B.
Insufficient project funding and ineffective use of resources
Answers
B.
Insufficient project funding and ineffective use of resources
C.
Disqualification of sellers and non-productive management efforts
Answers
C.
Disqualification of sellers and non-productive management efforts
D.
Non-productive management effort and inefficient use of resources
Answers
D.
Non-productive management effort and inefficient use of resources
Suggested answer: D