What are the identified risks for doing excessive decomposition in a WBS?
A.
Insufficient project funding and disqualification of sellers
B.
Insufficient project funding and ineffective use of resources
C.
Disqualification of sellers and non-productive management efforts
D.
Non-productive management effort and inefficient use of resources