Which technique is utilized in the Control Schedule process?

A.
Performance measure
Answers
A.
Performance measure
B.
Baseline schedule
Answers
B.
Baseline schedule
C.
Schedule network analysis
Answers
C.
Schedule network analysis
D.
Variance analysis
Answers
D.
Variance analysis
Suggested answer: D