Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

A.
Initiating
Answers
A.
Initiating
B.
Planning
Answers
B.
Planning
C.
Executing
Answers
C.
Executing
D.
Closing
Answers
D.
Closing
Suggested answer: C