The completion of the project scope is measured against the:

A.
requirements documentation.
Answers
A.
requirements documentation.
B.
project scope statement.
Answers
B.
project scope statement.
C.
project management plan.
Answers
C.
project management plan.
D.
work performance measurements.
Answers
D.
work performance measurements.
Suggested answer: C