When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.
event.
Answers
A.
event.
B.
response,
Answers
B.
response,
C.
perception.
Answers
C.
perception.
D.
impact.
Answers
D.
impact.
Suggested answer: A