Question 687 - CAPM discussion
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
A.
Communications management plan
B.
Human resource plan
C.
Quality management plan
D.
Procurement management plan