Which of the following includes how requirements activities will be planned, tracked, and reported?

A.
Configuration management plan
Answers
A.
Configuration management plan
B.
Scope baseline
Answers
B.
Scope baseline
C.
Requirements management plan
Answers
C.
Requirements management plan
D.
Schedule baseline
Answers
D.
Schedule baseline
Suggested answer: C