A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.
Manage Stakeholder Expectations.
Answers
A.
Manage Stakeholder Expectations.
B.
Monitor and Control Risks.
Answers
B.
Monitor and Control Risks.
C.
Plan Risk Management.
Answers
C.
Plan Risk Management.
D.
Report Performance.
Answers
D.
Report Performance.
Suggested answer: A