Question 703 - CAPM discussion

Report
Export

Which of the following is an output of Close Procurements?

A.
Accepted deliverables
Answers
A.
Accepted deliverables
B.
Organizational process assets updates
Answers
B.
Organizational process assets updates
C.
Managing stakeholder expectations
Answers
C.
Managing stakeholder expectations
D.
Performance reports
Answers
D.
Performance reports
Suggested answer: B