In which Project Cost Management process is work performance data included?

A.
Plan Cost Management
Answers
A.
Plan Cost Management
B.
Estimate Costs
Answers
B.
Estimate Costs
C.
Determine Budget
Answers
C.
Determine Budget
D.
Control Costs
Answers
D.
Control Costs
Suggested answer: D