To which knowledge area does the Collect Requirements process belong?

A.
Quality Management
Answers
A.
Quality Management
B.
Scope Management
Answers
B.
Scope Management
C.
Cost Management
Answers
C.
Cost Management
D.
Integration Management
Answers
D.
Integration Management
Suggested answer: B