The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.
Work performance reports, change requests, and risk register
Answers
A.
Work performance reports, change requests, and risk register
B.
Work performance data, project documents, and stakeholder engagement plan
Answers
B.
Work performance data, project documents, and stakeholder engagement plan
C.
Project charter, project management plan, and project documents
Answers
C.
Project charter, project management plan, and project documents
D.
Work performance data, stakeholder register, and team management plan
Answers
D.
Work performance data, stakeholder register, and team management plan
Suggested answer: C