A project stakeholder is requesting changes to the project plan. Which process group addresses this?

A.
Initiating Process Group
Answers
A.
Initiating Process Group
B.
Planning Process Group
Answers
B.
Planning Process Group
C.
Executing Process Group
Answers
C.
Executing Process Group
D.
Monitoring and Controlling Process Group
Answers
D.
Monitoring and Controlling Process Group
Suggested answer: D