Which set of competencies should a project manager have?

A.
Leadership, strategic and business management, and technical project management
Answers
A.
Leadership, strategic and business management, and technical project management
B.
Expertise in the Industry, leadership and business management, and bilingual skills
Answers
B.
Expertise in the Industry, leadership and business management, and bilingual skills
C.
Technical project management, expertise in every role, and PMP certification
Answers
C.
Technical project management, expertise in every role, and PMP certification
D.
Expertise in every detail on project activities. PMP certification, and leadership
Answers
D.
Expertise in every detail on project activities. PMP certification, and leadership
Suggested answer: A