During which process of Project Cost Management does a project manager produce the cost baseline?

A.
Estimate Costs
Answers
A.
Estimate Costs
B.
Control Schedule
Answers
B.
Control Schedule
C.
Determine Budget
Answers
C.
Determine Budget
D.
Develop Project Charter
Answers
D.
Develop Project Charter
Suggested answer: C