A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

A.
Monitor and Control Project Work
Answers
A.
Monitor and Control Project Work
B.
Direct and Manage Project Work
Answers
B.
Direct and Manage Project Work
C.
Close Project or Phase
Answers
C.
Close Project or Phase
D.
Perform Integrated Change Control
Answers
D.
Perform Integrated Change Control
Suggested answer: D